First Solar reported third-quarter 2026 net sales of $1.23 billion and reduced its full-year revenue and volume forecasts, saying tariff uncertainty and slower procurement have delayed orders. The manufacturer now expects 2026 module volumes of 16.0 GW to 17.0 GW and net sales of $4.6 billion to $4.9 billion, down from the $4.9 billion to $5.2 billion range it issued after the second quarter.

The revised outlook came alongside results showing $571 million in net income and a 58% gross margin. Net sales fell 23% year over year because First Solar sold fewer modules to third parties, but gross margin was about 20 percentage points above the prior-year quarter and net income rose 25%. The company also authorized a new $500 million share buyback.

Commercial shift

On its earnings call, management described how the company is adjusting its commercial and operational approach after the August Section 232 tariff proclamation. CEO Mark Widmar called the measure a structural change in US solar manufacturing policy and said First Solar expects nearly 80% of its global manufacturing footprint to be in the United States by 2027. He also said the company is the only fully integrated utility-scale solar manufacturer without dependence on a Chinese crystalline silicon supply chain and believes it is positioned to benefit.

Near-term demand, however, has been affected by several pressures. Widmar said developers are delaying module procurement for 2029 and 2030 while they work through interconnection constraints and local opposition to data-center projects, await further guidance on Foreign Entity of Concern rules, and assess how Section 232 minimum import prices and anti-stockpiling rules will be enforced.

Backlog and contracting

First Solar ended the quarter with a contracted backlog of 44 GW valued at about $13.5 billion, with deliveries scheduled through 2030. Since its second-quarter update, the company recorded 1.4 GW of US bookings at an average selling price of about 36 cents per watt.

CFO Alex Bradley said First Solar does not want to rely on the spot market for international volumes. Instead, it is moving toward project-specific contracts with defined delivery schedules, rather than the multi-year framework agreements covering multiple projects for very large customers that the company has used in the past. Bradley said that approach should allow more efficient operational planning and reduce working capital and warehousing costs, though it may slow the rate at which multi-year backlog grows.

Malaysia decision

Trade and tariff pressures have hit First Solar’s international Series 6 production in Southeast Asia. Its Vietnam plant is slated to supply semi-finished Series 6 modules to a newly inaugurated South Carolina finishing facility, while its Malaysia factory continues to make finished international modules. Widmar said the company expects to make a binary decision on the 1.8 GW Malaysia plant in the first half of 2027: operate it at full or near-full capacity, or shut production. Because Malaysian modules do not qualify for US Section 45X manufacturing tax credits and face freight and tariff costs, First Solar does not expect either outcome to materially affect run-rate earnings.

First Solar also announced a non-exclusive patent licensing agreement with perovskite company CubicPV just before the call, adding rights to its existing agreement with Oxford PV. The company plans to begin producing Series 6-form-factor perovskite modules at its Perrysburg, Ohio, facility in the first half of 2027 for field testing and durability validation. The call also covered perovskite investments and how forthcoming modules using First Solar’s CuRe technology compare on cost with crystalline silicon PERC and TOPCon competitors.

On legal matters, Widmar said First Solar will soon file its formal response in a warranty lawsuit brought by developer Swift Current Energy. He maintained that the company’s warranty terms govern any remediation and that First Solar will support obligations within its limited-liability warranty, but will not provide remedies outside those terms. Management also discussed ongoing disputes over the company’s TOPCon intellectual property.